155,754m3 of concrete used , which included 18,000 tonnes of reinforcement . One slab per work day was poured , and a total of 4,200 columns were poured over the length of the project .
Since the New Year , work on the non-clinical areas of the building — including commercial areas , kitchens and facilities management areas — have been completed . The high-voltage infrastructure is complete and the hospital has connected the supply feed from South Australia Power Network to the substation .
The new RAH will be completed in 2016 , so there is still much work to be done . Upcoming work includes completing the curtain