LITHKO - RIVER SPIRIT CASINO PROJECT
The Lithko crew places level 25 at the River Spirit project
THE RIGHT MIX FOR THE JOB Finding the perfect concrete mix is also vital to staying on schedule , as every other operation hinges on floors and load-bearing walls that have gained enough strength to keep moving forward .
“ We poured the structural deck typically at 2:00 a . m ., and by 3:00 p . m . that afternoon we poured columns and sheer walls — then by noon the next day we tensioned the post-tension slabs ,” says Duke . “ We had to have 3750 PSI on the concrete within 24-30 hours in order to make schedule . We also had to not just make the strength in the timeframe , but finish it .”
Countless tests and trial batches performed by local Tulsa-based supplier and partner Eagle Ready