AUSTRALIA
2016 , under budget and nearly a year ahead of schedule .
SAFETY ON THE GATEWAY “ The vision of the Gateway WA project was a safe and efficient transport network that provides an iconic gateway to Western Australia and the project ’ s mission was to safely deliver sustainable landmark infrastructure around Perth Airport and the Kewdale and Forrestfield freight precincts ,” states Spagnolo . “ Safety has always been at the forefront of what we have done and what we have delivered .” When a complex project with multiple high risk-posing components is at hand , a commitment to safety cannot simply be lip service . For the Gateway WA Alliance , safety is fully engrained in the workplace culture . The project has entailed what Spagnolo describes as a “ hierarchy of control ” including engineering , isolation , substitution and elimination to promote a high standard of safety that ultimately achieved concrete results . SUPPLIER PROFILE
WEST FORCE CONSTRUCTION
Employees : 70 -120 Established : 2006 Industry : Civil Construction
Services : Specialists in all aspects of the civil construction industry from earthworks to finished concrete & mechanical . Providers of skilled labour crews and plant hire .
Ongoing Projects : Roy Hill Chlorides Washing Facility , Beenyup Waste Water Treatment Plant , Australian Defence Facility Upgrade , Boral Crushing Facility , PTA Claisebrook Retaining Noise Walls , BHP Yandi Upgrade .
Management : Mike Murrey - Managing Director ; John Smith - Commercial Director ; Phil Clarke - Operations Director ; Paddy Kearns , Resources Director
Website : www . westforce . com . au www . gatewaywa . com . au 147