valued at $ 31 million , the other I-94 UPRR / STH 100 at $ 73 million .
The 76th Street Bridge Project was substantially complete on Nov 7 , 2014 and the I-94 UPRR / STH 100 Project completed Dec 19th , 2014 . The scope of work was very diverse , including nearly 6 million pounds of structural steel , 2.5 million pounds of steel reinforcement bar , 11,000 cubic yards of structural concrete , 200,000 cubic yards of earthwork , as well as 65 fully cased drilled shafts — eight of which were pier shafts for the railroad . The company was one of only three contractors that were pre-qualified to perform this work for the State of Wisconsin on the Zoo Interchange Project .
“ The drilled shafts required a considerable amount of testing ,” said Phil Griffith , project
“ We ’ re going to continue to pursue Projects in Wisconsin , we believe it to be a strong construction market with many opportunities , in fact there are several future projects that are currently on our radar ”
– Griffith concluded
www . walshgroup . com 85